Trending Schedule Development Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

What is the primary difference between critical path (CPM) and critical chain (CCPM) schedule approaches?‎

  a. There is fundamentally no difference b. CPM focuses on managing float while CCPM focuses on managing buffers c. CCPM focuses on extensive multi-tasking while CPM ‎ ... See More

Answers:
4
Followers:
Views:
763
Vote Count:
2
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago
Answers:
5
Followers:
Views:
643
Vote Count:
1
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago
Answers:
3
Followers:
Views:
199
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

Your project is experiencing resource constraints at certain times in the project timeline, Refer to below options for answer?‎

requiring you to adjust start and finish dates on the schedule. What tool is best to use in this situation?   a. Resource leveling b. Feeding buffer c. Critical‎ ... See More

Answers:
1
Followers:
Views:
170
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago
Answers:
5
Followers:
Views:
1946
Vote Count:
0
Answer should contain a minimum of 25 characters.
kamran syed's image
Question added by kamran syed Senior Manager Engineering PAK SHAHEEN CONTAINER SERVICES PVT LTD
7 years ago

How to schedule recurring invoices?‎

Need to send out invoices on a regular basis? Quick Books makes it easy to set them up automatically. Just schedule recurring invoices!‎

Answers:
1
Followers:
Views:
62
Vote Count:
0
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

The project schedule has finally been completed for the project. In reviewing the resource estimates, you?‎

notice that several key resources have been assigned multiple activities on several parallel network paths. You have also noticed that the resources for the different tim‎ ... See More

Answers:
0
Followers:
Views:
41
Vote Count:
0
Answer should contain a minimum of 25 characters.
sonhadji none's image
Question added by sonhadji none
10 years ago
Answers:
1
Followers:
Views:
44
Vote Count:
0
Answer should contain a minimum of 25 characters.
Mohamed Helal's image  
Answer added by  Mohamed Helal, Project Manager, GROUP CONSULT INTERNATIONAL
7 years ago

The near critical paths of a project may have small amounts of float -"little float"- as such, they must be completed in a timely manner or the overall project ... See More