The near critical paths of a project may have small amounts of float -"little float"- as such, they must be completed in a timely manner or the overall project plan may be impacted in the same manner as by a critical path.
Agreed with answers,
thanks for invite
the critical path is the path with zero float , the near critical path is the path with a small amount of float such that if any delays happen it may become critical
thanks for invition ,,,,,,,,,, i agree with experts answers