Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Your project is experiencing resource constraints at certain times in the project timeline, Refer to below options for answer?

requiring you to adjust start and finish dates on the schedule. What tool is best to use in this situation?

 

a. Resource leveling

b. Feeding buffer

c. Critical Path method

d. Resource smoothing

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/15
Waleed Hamdy
by Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

a. Resource leveling ............

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.