ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which is NOT an input to the Create WBS process?

Project Scope Statement Organizational Process Assets Scope Management Plan WBS Dictionary

user-image
تم إضافة السؤال من قبل مستخدم محذوف‎
تاريخ النشر: 2014/08/27
طﻻل صدقي عثمان arman
من قبل طﻻل صدقي عثمان arman , رئيس مجلس اﻹدارة والمدير العام , شركة عرمان للهندسة والمقاوﻻت المحدودة

WBS dictionary is not an input for Create WBS Process while the rest are ...

Salauddin Mohammad
من قبل Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

WBS dictionary is the output of create WBS process, so my answer to your question is "WBS dictionary"..

Faraz Shafiuddin Shafiuddin
من قبل Faraz Shafiuddin Shafiuddin , Business Analyst , National Guard Health

WBS Dictionary, as rest all are inputs, this is only a repository of terms and definitions and cannot be treated as a input.

WBS Dictionary will not be a direct Input, however it can be used as reference.

hossam azzam
من قبل hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

WBS Dictionary

hatem labib
من قبل hatem labib , Quality control manager , MISER consultant

WBS dictionary is output

Raafat Sallam
من قبل Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

WBS dictionary is one of the output of create WBS process

Antonio J Pedreño Avila
من قبل Antonio J Pedreño Avila , Project Manager , SEMI USA

WBS dictionary is one of the elements of the Scope Baseline therefore it is not an input, it is an output of the Create WBS process.

The Scope Baseline include:

1. Project Scope Statement

2. WBS

3. WBS dictionary

Mohamed Hamdy Kamal Riad
من قبل Mohamed Hamdy Kamal Riad , Senior Solution Architect , IBM

Fourth option 

WBS Dictionary

SunilKumar N
من قبل SunilKumar N , Senior Business Analyst / Project Manager , AlMusbah IT and Telecoms

The use of Work Break Down Structure (WBS) is bring down or breaking objects at atomic level and / or Managing Levels.

1) Project Scope Statement: This is used for breaking down scope.

2) Organizational Process Assets: In organisations the process tools, templates and key level documents which can be break down according to the project requirements.

3) Scope Management Plan: This is used to break down the scope at simple statement levels.

4) WBS Dictionary: This is a type of Glossary and /or Dictionary where concepts are already broke at atomic level. 

 

Conclusion: WBS Dictionary is a subset of Work Break Down Structure (WBS) hence this can't  be an input for WBS rest of all can be an Input.

Project Scope Management Plan is not an input to the WBS Creation process

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟