A. Project objectives, project scope description, project requirements B. Fund limitation, cost estimate, configuration management requirements C. Project specification, approval requirements, WBS D. Project boundaries, project deliverables, project acceptance criteria E. Constraints/ assumptions, initial defined risks, schedule milestones
The detailed project scope statement not include .
B. Fund limitation, cost estimate, configuration management requirements.
Those who has opted option "B", could you pls define Scope?
B. Fund limitation, cost estimate, configuration management requirements
B. Fund limitation, cost estimate, geometry management specification
the most accurate answer is "B ". I do agree with Mr "khairy" that WBS creation comes right after creating the project scope statement
b
B. Fund limitation, cost estimate, configuration management requirements
1.Fund limitation, cost estimation will be available in Bills of Quantities.
2.Management requirements will be internal documents.