ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are in process of creating the detailed project scope statement. All of the following are inputs to this process EXCEPT ?

A. Project scope B. Organizational project assets C. Preliminary project scope statement D. Approved change requests E. Scope baseline

user-image
تم إضافة السؤال من قبل Mohamed El Sayed , Project Manager , Saudi Post
تاريخ النشر: 2014/05/24
اسامه محمد عبد العزيز عيسى عيسى
من قبل اسامه محمد عبد العزيز عيسى عيسى , construction , Saudi Aribya

The project document is used to update the manual of the third edition of the Project Manual, which summarizes the processes, inputs and outputs that are often considered ...... and the integration and articulation of the project, the important integration procedures to complete the project, A work is a narrative of the products or services that will result from the project ...... This baseline includes all approved budgets except reserves

Khairy Khalil
من قبل Khairy Khalil , PROJECT MANAGER , NORPETCO FEED DESIGN REVIEW

E: Scope baseline

 

scope base line = scope statment + WBS + WBS dictionary

WBS creation comes after scope statment creation.

Muhammad samran
من قبل Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

Approved change requests

Mohamed AboulFotoh ELFeky
من قبل Mohamed AboulFotoh ELFeky , System Analysis/Arch, Technical/Project Manager , Orange Soft

Organizational project assets

Tapesh Ghatak
من قبل Tapesh Ghatak , Project Control Manager , NATIONAL CONTRACTING COMPANY LIMITED – Saudi Arab. P.O.Box 90. Al-Khobar 31952. www.ncc.com.sa

Yes, agree. Without planing execution may negative effect on the project

Mohamed Omar  samatar
من قبل Mohamed Omar samatar , Relationship Officer , premierbank at Somalia

 D is the best response. The project scope management plan includes preparation of a detailed project scope statement, creation of the WBS, and a process specifying how formal verification and acceptance of the completed project deliverables will be obtained. 2.Answer A is correct. A properly sized work package is one that is small enough to allow for reliable estimates for required resources and duration. Answers B, C, and D are incorrect because they assume that you are working toward some artificial target that does not contribute to appropriately sized work packages. 3.Answer A is correct. The project charter is one of two defined inputs for the collect requirements process. (The other input is the stakeholder register.) Answer B is incorrect because the requirements traceability matrix is an output for the collect requirements process. Answers C and D are incorrect because they refer to inputs from other processes.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟