The detailed project scope statement includes all of the following EXCPET ?

A. Project objectives, project scope description, project requirements B. Fund limitation, cost estimate, configuration management requirements C. Project specification, approval requirements, WBS D. Project boundaries, project deliverables, project acceptance criteria E. Constraints/ assumptions, initial defined risks, schedule milestones

user-image
Question added by Mohamed El Sayed , Project Manager , Saudi Post
Date Posted: 2014/04/29
Fredy Makram Labib
by Fredy Makram Labib , R&D manager , Universal for home appliances

B

Ramy Zakher
by Ramy Zakher , Executive director , EEP

The detailed project scope statement not include .

 

B. Fund limitation, cost estimate, configuration management requirements.

Khairy Khalil
by Khairy Khalil , PROJECT MANAGER , NORPETCO FEED DESIGN REVIEW

Answer: c WBS creation comes after detailed scope statement.

Mohammad Aslam
by Mohammad Aslam , Projects Manager , National Aluminium & Steel Factory

Those who has opted option "B", could you pls define Scope?

Elsayed Abdel Monem Sayed Abdel Halim  PMP
by Elsayed Abdel Monem Sayed Abdel Halim PMP , Projects Manager , Almenah for engineering contacting

B. Fund limitation, cost estimate, configuration management requirements 

Salauddin Mohammad
by Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

Answer is "B".

Radar Abdulaziz
by Radar Abdulaziz , field engineer , GE Oil & Gas

B. Fund limitation, cost estimate, geometry management specification

Basem Nofal
by Basem Nofal , Manager - Technical and Construction , consolidated Contractors international company - Qatar

the most accurate answer is "B ". I do agree with Mr "khairy" that WBS creation comes right after creating the project scope statement

Elias Assaf
by Elias Assaf , Projects Manager , Private Engineering Office

b

ARUN BENADICK
by ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company

B. Fund limitation, cost estimate, configuration management requirements 

 

1.Fund limitation, cost estimation will be available in Bills of Quantities.

2.Management requirements will be internal documents. 