Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In an EPC project after how much percentage progress of civil work, should piping work be started?

user-image
Question ajoutée par Atul Pratap , Construction Manager , PUNJ LLOYD LTD.
Date de publication: 2017/08/19
karthick sankarabalan
par karthick sankarabalan , Abu Dhabi Gas Industries Limited (GASCO)

Piping work will start after completion of 50 % civil work .

Rajesh Pawar
par Rajesh Pawar , Sr. Project Manager , Toyo Engineering India Pvt. Ltd

Soil compaction and leveling shall be finished. Main Pipe rack installation work shall be started.

Mubeen Khalid
par Mubeen Khalid , GIS-PID Mechanical/Piping/Welding , INTERTEK SAUDI ARABIA CO.

We can start piping works after 30% complition of the civil work.

Fahim Shah
par Fahim Shah , Lead Materials Engineer , Jaocbs Zate

It should be after around 30%

It is not only Civil, but also structural works . The percentage progres should be about 25 to 28%

jaydip lathiya
par jaydip lathiya , Sr. Project Engineer. , Reliance project & Property Management and Services

We can start piping work after 30% of civil work completion.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?