ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

In an EPC project after how much percentage progress of civil work, should piping work be started?

user-image
تم إضافة السؤال من قبل Atul Pratap , Construction Manager , PUNJ LLOYD LTD.
تاريخ النشر: 2017/08/19
karthick sankarabalan
من قبل karthick sankarabalan , Abu Dhabi Gas Industries Limited (GASCO)

Piping work will start after completion of 50 % civil work .

Rajesh Pawar
من قبل Rajesh Pawar , Sr. Project Manager , Toyo Engineering India Pvt. Ltd

Soil compaction and leveling shall be finished. Main Pipe rack installation work shall be started.

Mubeen Khalid
من قبل Mubeen Khalid , GIS-PID Mechanical/Piping/Welding , INTERTEK SAUDI ARABIA CO.

We can start piping works after 30% complition of the civil work.

Fahim Shah
من قبل Fahim Shah , Lead Materials Engineer , Jaocbs Zate

It should be after around 30%

It is not only Civil, but also structural works . The percentage progres should be about 25 to 28%

jaydip lathiya
من قبل jaydip lathiya , Sr. Project Engineer. , Reliance project & Property Management and Services

We can start piping work after 30% of civil work completion.

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟