You and the project team are planning the work of the project. In addition to all of the planning activities...

 that you're engaged in, part of the team has been reviewing the customer requirements, and has started to outline a work breakdown structure as well as create elements of the WBS dictionary, breaking down the work packages into smaller increments. The most accurate way of describing this is that you are creating:

a. A milestone list

b. A deliverable list

c. An activity list

d. A scope elaboration

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/16
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – The key phrase in the question is ‘breaking down work packages into smaller increments’ which is the

definition of creating activities. Milestones and deliverables are higher levels above the work package.

Scope elaboration is a red herring

adnan sabir
par adnan sabir , Senior Branch Accountant , Bindawood Group of Companies

C. Active list because first you have to ensure the active members.

Usman Islam
par Usman Islam , Yard Manager , Kirtanlal Scaffolding & Formwork

c is the correct answer.............

sardar mardookhy
par sardar mardookhy , PMP certified Project manager , MCCI

Breaking down the work pachage will be activity list

Ghada Eweda
par Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

The correct answer is already picked by experts. thanks

Mohamed Helal
par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation  it is ............. a. A milestone list