Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following is displayed as an S curve?

 

A. Cost baseline

B. Critical path

C. Gantt

D. Schedule baseline

 

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/07
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The correct answer is cost baseline

ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

On S-Curve you can display cost, physical progress, manhours etc. However based on the question I will vote for A. Cost Baseline.

Robert Malak
par Robert Malak , Projects Manager , Ankido Oil Services for General Contracts DMCC

Thank you for the invitation, I believe the answer is A.

S curve is not a constant. sure there is one at the beginning of the project as constructed from the cost baseline, later it will be reconstructed and compared to the initial one to identify, compare and take corrective measures to control your project performance. Every month the S curve will slightly change its shape.

Thanks

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

Iagree the option A

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. Sorry, I have no knowledge about it.

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem option A-Cost baseline is a good answer.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option A

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?