ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following is displayed as an S curve?

 

A. Cost baseline

B. Critical path

C. Gantt

D. Schedule baseline

 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2017/04/07
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The correct answer is cost baseline

ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

On S-Curve you can display cost, physical progress, manhours etc. However based on the question I will vote for A. Cost Baseline.

Robert Malak
من قبل Robert Malak , Projects Manager , Ankido Oil Services for General Contracts DMCC

Thank you for the invitation, I believe the answer is A.

S curve is not a constant. sure there is one at the beginning of the project as constructed from the cost baseline, later it will be reconstructed and compared to the initial one to identify, compare and take corrective measures to control your project performance. Every month the S curve will slightly change its shape.

Thanks

يوسف دمدوم
من قبل يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

Iagree the option A

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. Sorry, I have no knowledge about it.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem option A-Cost baseline is a good answer.

hisham abu dagga
من قبل hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option A

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟