A. All of the other alternatives apply.
B. The slack in the path containing this activity will increase.
C. The total cost for this activity has decreased.
D. The critical path is also reduced.
E. Manpower from this activity can be assigned to other activities.
__________Thank you for the invitation
Option B
_
In my opinion, The appropriate option is B. The slack in the path containing this activity will increase.
In my opinion option E is most appropriate & thanks for the invite.
Appreciation for your invitation. It is Option B.
B. The slack in the path containing this activity will increase
Thank you invitation.I seem option A. All of the other alternatives apply is good answer.
Thank you for the invitation. My answer is B