A Schedule Management Plan is developed in which of the following knowledge areas?

 A. Project Time Management B. Project Scope Management C. Develop Project Management Plan D. Project Cost Management

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: A Schedule Management Plan is developed as part of "Develop Project Management Plan"