Which of the following might require rebaselining of the cost baseline?

 A. Updates to the cost management plan B. Budget updates C. Revised cost estimates D. Corrective action

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
RAJ DAHIYA
by RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

B. Budget updates....................

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: Budget updates might require cost rebaselining .

Ali Chenah
by Ali Chenah , matériaux de construction/ construction metaliique , BATICIM -ALGERIE

   Mises à jour du plan de gestion des coûts  apres des mesures correctives

 

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

 Option B is the correct choice.