Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for Laurel's Theater Productions. Your new project is coming in over budget and requires a cost change through the cost?

change control system. You know all of thefollowing statements are true regarding Cost Control except for which one? A. Changes are reflected in the cost baseline. B. Performance is monitored to detect variances. C. Changes are monitored and reflected in the project scope. D. Changes are monitored so that inappropriate changes do not get into the cost baseline.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/01/24
RAJ DAHIYA
by RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

Changes are monitored and reflected in the project scope. 

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the best choice.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: Cost Control tracks project performance to detect variances and reflect them in the cost baseline. It's also used to prevent inappropriate changes from getting into the cost baseline.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.