Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about?

his PMI certification and was subsequently fired. Unfortunately, he didn't create a project charter or a preliminary scope statement. You are ready to elaborate the deliverables and requirements of the project and know that you can use one of the following in place of the charter or preliminary scope statement. Which one can you use?

A. Expert judgment

B. Strategic plan

C. Product scope description

D. Business justification

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/12/17
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Product scope description

The product scope description can be used as an input to the Scope Definition process when the project charter and/or preliminary project scope statement are missing.

andre andre
by andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

MY Option will be -B - Strategic plan.

Minhajul Islam
by Minhajul Islam , Sr. Computer Programmer

B.

Due to lack of project charter and project scope which must generate during the initial phaze. It is prefere to generate an Strategic Plan which will help to visualise project deliverables and requirements. 

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option B

As a manager I will provide or use a strategic plan which will improve my company.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.