Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

All of the following are outputs of the Integrated Change Control process except for which one?

A. Validated defect repair

B. Approved corrective actions

C. Requested changes

D. Project scope statement updates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/09/30
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Approved change requests are an output of this process, not requested change requests. The other tools and techniques of this process are rejected change requests, project management plan updates, approved preventive actions, approved defect repair, and deliverables

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.