Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are in the process of controlling changes to the project scope. All of the following are outputs of this process EXCEPT: ?

A. Requested changes B. Project management plan updates C. Recommended corrective actions D. Work performance information E. Scope baseline updates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/04/24
Mohamed Saber
by Mohamed Saber , Production Manager , AL-BLAGHA INDUSTRIAL COMPANY ( DAMMAM SHIPYARD )

A                                 requested changes

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Work performance information 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.