Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Should we revise the baseline schedule after approval of each project control change notice?

Some time a change notice is less value and some it is more value. When should we revise baseline schedule.

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/05/31
Ahmed Mohamed Abdel Kader Al-Assar
by Ahmed Mohamed Abdel Kader Al-Assar , Project Control Engineer , QU

Revised shcedule mean that the change impacted on the BL Schedule and extension of time has been approved, in this case the answer of your question is YES

ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The following examples illustrate the varying contract conditions that define the need for a recovery schedule: • If the project falls behind schedule more than 14 days or 10% of the remaining duration, whichever is less, for non-excusable delays; • In the event that the Progress Schedule Update indicates that the Project, or progress towards any interim milestone, falls 20 or more work days behind schedule; • When requested by the Owner or Engineer; • When the owner determines that the contractor is behind any mandatory specific milestone or completion dates or any interim milestone completion date; • When the contractor determines that the progress schedule requires revision for any reason; and, • When departure from the existing schedule makes it apparent that the project will be late. 

Razi Ullah
by Razi Ullah , Senior Cost Engineer , Peace River Hydro Partners

After approval of any significant scope change which impacts the total duration of the project, the baseline schedule needs to be revised.

Gandhi Mohankumar
by Gandhi Mohankumar , Construction Project Manager , Golden Sand Engineering Construction

Revised schedule means, with reference to Baseline plan, a revised plan will be submitted to client for approval.

Skanda Kumar
by Skanda Kumar , Associate Manager , Excelsoft Technologies Pvt Ltd

Imho, we should not change the final baseline after scope freeze and final deployment. Scope creeping is usually handles differently. Eacb change should be managed by proper change control mechanism, this will allow us to xompare final baselines with changes made. A change usually do not ask for a baseline revision.

Lamya Alkhoori
by Lamya Alkhoori , Architecture consultant , Islamic Architect and engineering consultancy office

The revision of a starting point for projects is most certainly essential when there are changes in projects and decision making processes. Different plans require different outcomes therefore different consequences are expected when the project doesn't go according to plan and therefore must be weighed according to the extent of these consequences by reviewing and comparing the different approaches to the project proposals 

Noel Lane
by Noel Lane , Director of Operations , Integrated Building Company

Every schedule, just like every plan, requires constant monitoring and adjustment as situations and project development occurs.

The original schedule is a baseline measure of performance for achieving business objectives.

Schedules, like plans, must be adjusted or revised as necessary to meet changing performance and environments, so that schedule objectives are met timely in order to fulfill the plan.

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.