Where does comparing actual to baseline schedules, examining the statement of work, understanding cost overruns, and assessing risk all occur?

 A. Stakeholder meeting. B. Resource leveling activity. C. Project audit. D. Contract negotiation.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2018/02/08
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Project audit. -----------------------