What is the difference between Revised Baseline Schedule & Revised Construction Schedule in construction planning?

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/07/31
Mohamed Medhat  Mohamed Hamed
by Mohamed Medhat Mohamed Hamed , planning & cost Engineer , Acciona

Revised Baseline Schedule is the General term which include Engineering, Procurement, Construction ... etc 

So, the revised baseline means revised for all items but revised construction schedule means revised for the construction WBS only. 