The inputs of the Performance Reporting process include all of the following except for which one?

 

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/12/17

C. Forecasted completion... thats what does not come under Performance Reporting process

Mohamed Shaker Eissa
by Mohamed Shaker Eissa , Training & SFE Manager , Abbott Nutrition

Question number 2 ( Work Performance Informantion )

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable answer is  A. Performance reviews

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option C- Forecast Completion. Many thanks for your invitation.

Ahmed Hejazi
by Ahmed Hejazi , Projects Manager , Jadat Itqan Consulting - JIC

Forecasted completion is not an input to performance reporting process 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

I will go with option C .