Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The inputs of the Performance Reporting process include all of the following except for which one?

 

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/12/17

C. Forecasted completion... thats what does not come under Performance Reporting process

Mohamed Shaker Eissa
par Mohamed Shaker Eissa , Training & SFE Manager , Abbott Nutrition

Question number 2 ( Work Performance Informantion )

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable answer is  A. Performance reviews

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option C- Forecast Completion. Many thanks for your invitation.

Ahmed Hejazi
par Ahmed Hejazi , Projects Manager , Jadat Itqan Consulting - JIC

Forecasted completion is not an input to performance reporting process 

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

I will go with option C .

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?