Complete final contract performance reporting and verify product is done in?

 

A. Conduct Procurements

B. Close Procurements

C. Plan Procurements

D. Administer Procurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/02

Option B is the relevant answer.

CHANDRASEKHAR BASU
by CHANDRASEKHAR BASU , MATERIAL COORDINATION MANAGER , FULL TIME EMPLOYEE Multinational Petroleum GROUP INDUSTRY, MILAN , ITALY

The final Product to be in complience serves specific requirement that is worth for as per the applicability & quality assurance .