Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

During what part of Procurement Management process does procurement negotiations happened?

A. Plan Procurements

B. Administer Procurements

C. Conduct Procurements

D. Close Procurements

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/06/17
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The correct answer is Option C - Conduct Procurements.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with Option C

With greetings and appreciation

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.