ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Consider the following scenario: the contract is a fixed price/lump sum contract. The change control procedure?

 in place states that written authorization for all changes is required. You noticed that there is a% budget overrun due to one of the project team members verbally instructing a supplier to perform work outside of its contracted scope of work. How would you as the project manager address this project team member for the apparent disregard for following directions? What conflict resolution style will you employ? A. Compromising B. Problem-solving C. Forcing D. Smoothing E. Withdrawal

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2018/02/21
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Problem-solving ------------------

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟