ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What is the main deference between CPM and PERT technique in scheduling project activities ?

user-image
تم إضافة السؤال من قبل Ahmed Khater , ID& Fit- Out Construction Manager , Harmony Atelier Interior Design& Decoration
تاريخ النشر: 2015/12/30
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

PERT (Program Evaluation and Review Technique) is a technique for estimating that applies an average of optimistic, pessimistic and most likely estimates when there is uncertainty with the individual activity estimates.  CPM (Critical Path Method) is a method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model.

Riad Boughannam
من قبل Riad Boughannam , Civil Engineer , Self Employed

CPM and PERT are both used in Project Management.

CPM is usually used in construction project that could be repetative some times, whereas the PERT technic is mostly used in R&D projects that are mostly non repetative.

PERT is Probabilistic model while CPM is Deterministic and depends mainly on well defined and recognizable tasks/activities.

In CPM time is estimated using a single estimate while in PERT 3 time estimates are used ( optimistic, most probable and pessimistic).

So generally CPM is used when the project has predictable activities(such as construction projects) while PERT is used on projects with upredictable activities (such as R&D projects). 

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟