ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The artificial activity that an activity following it, can't start unless the preceding activity is complete, known as A.event B.free float C.dummy

user-image
تم إضافة السؤال من قبل Tala Baker , Tenders, Contracts & PMO Coordinator , Ventures Middle East (VME)
تاريخ النشر: 2015/05/28
Amit Hela
من قبل Amit Hela , Assistant General Manager Project Planning & Scheduling , Primetals Technologies India Private Limited joint venture of Mitsubishi Heavy Industries and partne

Its a dummy activitty. The answer is C

Paolo Borchetta
من قبل Paolo Borchetta , Managing Director , NIMM International Mauritanie Mining

The definition is "logic dummy" activity, however there is a slight improvement in the definition.

Logic dummies in CPM serve to represent the logic sequencing connection between a prior set of activity and a following activity, the latter which does not require100% but only some of preceding activities to be completed in order to start. It is normally shown in broken lines.

In short there a logic sequencing between the activities but the latter is not100% dependent from the former.

it was introduce to preserve the integrity of the logic sequencing and to avoid contamination of the critical path.

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

C >>>>>>>>>>>>>>>>>>>>>>> dummy

sameera khalil
من قبل sameera khalil , Site Engineer , Freelancer

C is my answer dummy activity

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟