Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The artificial activity that an activity following it, can't start unless the preceding activity is complete, known as A.event B.free float C.dummy

user-image
Question ajoutée par Tala Baker , Tenders, Contracts & PMO Coordinator , Ventures Middle East (VME)
Date de publication: 2015/05/28
Amit Hela
par Amit Hela , Assistant General Manager Project Planning & Scheduling , Primetals Technologies India Private Limited joint venture of Mitsubishi Heavy Industries and partne

Its a dummy activitty. The answer is C

Paolo Borchetta
par Paolo Borchetta , Managing Director , NIMM International Mauritanie Mining

The definition is "logic dummy" activity, however there is a slight improvement in the definition.

Logic dummies in CPM serve to represent the logic sequencing connection between a prior set of activity and a following activity, the latter which does not require100% but only some of preceding activities to be completed in order to start. It is normally shown in broken lines.

In short there a logic sequencing between the activities but the latter is not100% dependent from the former.

it was introduce to preserve the integrity of the logic sequencing and to avoid contamination of the critical path.

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

C >>>>>>>>>>>>>>>>>>>>>>> dummy

sameera khalil
par sameera khalil , Site Engineer , Freelancer

C is my answer dummy activity

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?