Free float is mainly used to?

(A) Identify the activities which can be delayed without affecting the total float of preceding activity

(B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

(C) Establish priorities

(D) Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

user-image
تم إضافة السؤال من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
تاريخ النشر: 2016/08/08
Mahmoud Youssef
من قبل Mahmoud Youssef , Purchasing & Planning Manager , Delta Textile Egypt

to calculat market capitalization  by taking the equity's price and multiplying it by the number of shares readily available in the market

 

Rami Assaf
من قبل Rami Assaf , Plant Manager , Al Manaseer group

Thanks for invitation

I am agreeing with my colleague’s answer

Arshad Hussain
من قبل Arshad Hussain , Senior Manager Operations , Pakistan Revenue Automation Pvt Ltd

It is mainaly used for calculating market capitalization of an index. 

safi eljim bousaada
من قبل safi eljim bousaada , Senior project manager, certified PMP, PSM-I, PSPO-I , Saphir Consult

The free float gives options, to the manager, for delaying the start date of the activity, or to extend their execution time, without delaying the early start date of its successor. So here, the preceding activity is not concerned by the free float.

B) is the correct answer

Piotr Teteruk
من قبل Piotr Teteruk , IT Project Manager Roche , Roche

Free-float capitalization can also be called float-adjusted capitalization. The free-float method is considered a better way of calculating market capitalization, because it provides a more accurate reflection of market movements and stocks actively available for trading in the market. Instead of using all of the active and inactive shares, as with the full-market capitalization method, the free-float method excludes locked-in shares such as those held by insiders, promoters and governments.

In another words  - it is the amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.

Hameed mosad Ala hsab
من قبل Hameed mosad Ala hsab , مشرف هندسي , اوالتصميم والتخطيط والأشراف على التنفيذ

1- float(ing) ; flotation and buoying up ; float(ing) ; flotation ; keeping afloat ;

2-TIMBER FLOATING

3-company floatation

 

Luis Pujol
من قبل Luis Pujol , ROB Coordinator , Tecnicas Reunidas

I think it's a basic data to have an Helicopter View of your project evolution. I need always to know my free float. Free float show me the amount of time that an activity can be delayed without delaying the Early Start of its successor activity.

Total float is what we are aware of, and is commonly referred to as a float. Total float ( or slack) is the amount of time that an activity can be delayed without delaying the project completion date. On a critical path, the total float is zero. 

Rohanjit Menon PMP
من قبل Rohanjit Menon PMP , Senior Manager Business Development , Zuti Engineering Solutions

Hi Imran,

From what I know, Free Float is the time you can delay an activity without affecting the successor activity.

Let's say there is an activity of laying concrete which has a free float of2 days to the subsequent activity of say laying floor tiles. So the concrete can be delayed by up to2 days from its original schedule without affecting the floor tile activity.

Free float may be useful while resource smoothing (prevent over allocation over a resource limit), so as not to affect the critical path.