La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 6 années

Should we revise the baseline schedule after approval of each project control change notice?‎

Some time a change notice is less value and some it is more value. When should we revise baseline schedule.‎

Réponses:
7
Adeptes:
Vues:
71
Vote Count:
3
La réponse doit contenir un minimum de 25 caractères.
ZULFIQAR ALI's image
La question a été ajoutée par ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
Depuis 6 années

Should we revise the baseline schedule after approval of each project control change notice?‎

Some time a change notice is less value and some it is more value. When should we revise baseline schedule.‎

Réponses:
7
Adeptes:
Vues:
71
Vote Count:
3
La réponse doit contenir un minimum de 25 caractères.
Mike Emerson Pasaron's image
La question a été ajoutée par Mike Emerson Pasaron Safety Officer Arabian Petrochemical Co. (PETROKEMYA)
Depuis 10 années
Réponses:
3
Adeptes:
Vues:
113
Vote Count:
0
La réponse doit contenir un minimum de 25 caractères.
Ahmed Mohamed Abdel Kader Al-Assar's image  
La répondre a été ajoutée par  Ahmed Mohamed Abdel Kader Al-Assar, Project Control Engineer, QU
Depuis 6 années

Revised shcedule mean that the change impacted on the BL Schedule and extension of time has been approved, in this case the answer of your question is YES

Signaler CV
ZULFIQAR ALI's image  
La répondre a été ajoutée par  ZULFIQAR ALI, Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Depuis 6 années

The following examples illustrate the varying contract conditions that define the need for a recovery schedule: • If the project falls behind schedule more than 14 days o ... Voir Plus

Signaler CV
Default profile image  
La répondre a été ajoutée par  Samar Abu Shaban , Regional HR Operations manager, souq.com
Depuis 10 années

Fraud in the work place might happened and should be dealt with it in immediate action yet after have enough evidence; also, remember that you shouldn't be emotional ... Voir Plus

Signaler CV
Default profile image  
La répondre a été ajoutée par  Gandhi Mohankumar , Construction Project Manager, Golden Sand Engineering Construction
Depuis 6 années

Revised schedule means, with reference to Baseline plan, a revised plan will be submitted to client for approval.

Signaler CV
Noel Lane's image  
La répondre a été ajoutée par  Noel Lane, Director of Operations, Integrated Building Company
Depuis 6 années

Every schedule, just like every plan, requires constant monitoring and adjustment as situations and project development occurs. The original schedule is a baseline measur ... Voir Plus

Signaler CV
Razi Ullah's image  
La répondre a été ajoutée par  Razi Ullah, Senior Cost Engineer, Peace River Hydro Partners
Depuis 6 années

After approval of any significant scope change which impacts the total duration of the project, the baseline schedule needs to be revised.