Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Consultant issued a non conformance for the work which is under progress. My question is, was there any ISO standard with which I can defend?

As per project protocol he supposed not to issue non conformance for work under progress. Kindly share your ideas.

user-image
Question ajoutée par Hassan Shaik Ali , MEP Commissioning Manager , Medgulf Construction Company WLL
Date de publication: 2014/04/16
Mohamed Gaber
par Mohamed Gaber , Quality & Development General Manager , International Company For Food Industries

The consultant; by issuing the nonconformance, even in the under progress activities, he did the right job, and you have to define the root cause and the corrective action, otherwise tell me how you can improve your activities and get ISO's certificate . You cannot say I am in under progress, and I did not accept this non conformance. You have to know as maximum as the consultant raises non conformances, this will help you  to improve yourself and finally you  will get the ISO's certificate. And you not need to defend, Just accept the non conformance and go forward.

Mohamed Attia Ibrahim Attia
par Mohamed Attia Ibrahim Attia , quality and food safety manager at SEDRA group , سدرة للحلويات والمعجنات

this will help you  to improve yourself and finally you  will get the ISO's certificate. And you not need to defend, Just accept the non conformance and go forward

Ahmad Khreasat
par Ahmad Khreasat , Risk and Quality Officer , Royal Scientific Society - Policies & Risk Dept.

The ISO adopts the proactive approach in business management. I will second your consultant decision

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?