Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The CPM calculates the earliest start date, earliest finish date, and latest finish date for each activity. ?

Which of the following statements are true regarding the critical path of a project schedule? A. The float/slack time is determined by subtracting the early start date from the early finish date B. The float/slack time is determined by subtracting the early start date from the finish date C. None of the statements are true D. Any project activity with the slack time of zero or greater is considered a critical path

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/05/22

Hello everyone, I want to meet a good girl for a long time, but I just can't do it, it's good that a friend advised the dating site https://www.matchtrace.com/best-dating-sites-for-nerds/. Here I quickly found a pair for myself and now I can feel not lonely. Always live acquaintances with partners who are right for me. I recommend this resource to everyone.

Anthony Hall
par Anthony Hall , IT Expert , Itissalat Al-maghrib

There are so many dating websites but really few of them are worthy. That's why I usually keep the places where I meet people with me. But now I want to speak them out. First of all, grindr review helped me to find someone people for me.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. The float/slack time is determined by subtracting the early start date from the finish date

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?