You have been recently been assigned to provide an accurate project schedule for constructing a new 50-story casino, in Las Vegas, ?

Nevada. You are evaluating the network diagram for the construction project, and are using the forward pass calculations to construct the schedule. You are trying to calculate the earliest start time for laying the foundation of the building. The expected duration for this task is days. The task must be completed within days, while the expected completion is within days. The latest finish time is days. Based on this information, what is the earliest start time of this task? A. Not enough information is provided B. C.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/03/06
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Not enough information is provided