Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following scheduling techniques focuses on managing buffer activity durations and the resources applied to ?

the planned scheduled activities, instead of managing the total float of network paths? A. Monte Carlo analysis B. Variance analysis C. Critical path method D. What-if scenario analysis E. Critical chain method

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/03/13
Dalia safey
par Dalia safey , nursing administration and staff development , Cairo University Hospitals

the planned scheduled activities, instead of managing the total float of network paths?

E. Critical chain method

Tahir Aziz
par Tahir Aziz , Data Entry Operator , Federal Board of Revenue

D. What-if Scenario analysis

akhtar bebal
par akhtar bebal , Chief accountant /credit controller , Coca-cola

we wanted to change it back to an Auto Schedule Mode…or extend the finish date to be the complete sequence… Note: This course was designed in collaboration with author Bonnie Biafore. Lynda.com is a PMI Registered Education Provider. This course qualifies for professional development units (PDUs).

 

 

 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Critical chain method --------------

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?