Which of the following scheduling techniques focuses on managing buffer activity durations and the resources applied?

to the planned scheduled activities, instead of managing the total float of network paths? A. Monte Carlo analysis B. Variance analysis C. Critical path method D. What-if scenario analysis E. Critical chain method

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/01/30
Tahir Aziz
par Tahir Aziz , Data Entry Operator , Federal Board of Revenue

1) Monte Carlo analysis. 2) Variance analysis. 3) Critical path method. 

Alam Hamad
par Alam Hamad , Coordinator , United Nations World Food Prgram

This will be according to the budget and time frame.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Critical chain method ----------------