What should you as the project manager do in the event of reduced funding on your project?

 A. Perform detailed financial analysis and renegotiate for adequate funding. B. Only do as much work as the new budget permits and document actions taken. C. Inform in customer that the project will be delayed an adjust resources accordingly. D. Inform the customer of impacts and negotiate a change in scope. E. Abandon the project until funds are made available.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/02/21
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Abandon the project until funds are made available.