You have just been assigned a new project within your organization. After performing an initial analysis, it has become obvious that...

you will not have enough resources to complete the project by the requested due date. You bring your analysis back to the sponsor and to senior management, who respond with, "just do the best you can". In looking at various scheduling techniques, which of the following would be the

best scheduling approach to handle this situation?

a. Critical Path method

b. Precedence diagramming method

c. Resource leveling heuristics

d. Critical chain method

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2016/05/16

Answers should be 

d. Critical chain method