The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _ budget.?

A. In-process.

B. Preauthorized.

C. Unauditable.

D. Contingency.

E. Undistributed.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/04
يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option E

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option E is the correct choice.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Undistributed --------------------

Mohamed Ifham
par Mohamed Ifham , Quantity Surveyor , Al bandary Group

Option Lock E

E. Undistributed.