Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process?

The WBS changes might in turn  require which of the following?

A. Scope changes

B. Schedule revisions

C. Risk response changes

D. Cost changes

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/06/03
ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The correct answer is B.

B. Schedule revisions

Aneesh Shandilya
par Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option B - Schedule revision is required.

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option B

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the best choice.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?