Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. is not a concern of the project manager.
B. is concerned with naming all activities performed, the end products which results and the resources consumed.
C. is a subset of configuration management and as such is performed by CM specialists.
D. None of the other alternatives apply. E. entails managing the project's work content
Answer: B ----------------------------------
Thank you for the invitation
I agree the option E
Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?