Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller?

<p><strong>more manageable components?</strong></p> <p><strong>A. Plan Scope Management </strong></p> <p><strong>B. Define Scope </strong></p> <p><strong>C. Validate Scope </strong></p> <p><strong>D. Control Scope </strong></p> <p><strong>E. Create WBS</strong></p>

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/08
Divyesh Patel
par Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

E. Create WBS

WBS....it provides a structured vision tgat guides tge project team exactly what iscto be delivered.

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
par VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Create WBS---A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverable

Bilal Safdar
par Bilal Safdar , Project Civil Engineer , Bulleh Shah Packaging (Pvt) Ltd (Stora Enso & Packages Ltd JV)

(E)- WBS

Alex Al Yazouri
par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

E. Create WBS

A work breakdown structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components.

 

Ibrahim Hussein Mayaleh
par Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

It is the Work Breakdown Structure that is used in both Project Management as well as Systems Engineering. (E)

Abiola Adebisi
par Abiola Adebisi , Real Property Project Officer , Government of Canada

create Work Breakdown Structure

Elke Woofter
par Elke Woofter , Project Assistant , American Technical Associates

E) Create WBS is my answer

Mahmoud Awwad
par Mahmoud Awwad , Project Manager , Gulf Engineering and Industrial Consultancy

E. Create WBS is the correct answer

Chayan Purkayastha
par Chayan Purkayastha , Project Manager , CH2M Hill

E-Create WBS.  Work breakdown structure splits the activities.