Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is an activity that consumes no time or resources and shows only that a dependency exists between two activities called?

 

A. A milestone

B. A dummy activity

C. Both1) A milestone and2) A dummy activity

D. A hammock

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/01/13
DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My opinion is option B is correct.

Syed Kashif Abbas Jaffery
par Syed Kashif Abbas Jaffery , Business development and Capture Manager , LN Technology/ App maisters inc. USA

Activity is effort in time, if there is no one needed for efforts and there is no time taken by it, it's not activity. So my answer is B (A DUMMY ACTIVITY)

Noxolo Lewu
par Noxolo Lewu , Project Coordinator , Sanlam

A milestone - A milestone is an activity that has been accomplished already in a project. A milestone does not consume any resources, it is resource or time that has already been used by the project.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Option B is correct one ---------------------------------------

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is A Milestone & thanks for the invitation.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?