A. Fast tracking is the process of increasing the schedule by overlapping various project tasks.
B. One of the advantages of fast-tracking is that it can often lead to reduced rework and reduces project risks.
C. None of the statements are true
D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.
E. Fast tracking involves performing activities sequentially
The most suitable option is
C. None of the statements are true
D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.
Right Answer is Option E.
Option A is wrong: Fast Track decreases schedule
Option B is Wrong: Doesnt reduce rework or reduce risk, May Increase Risk
Option D is wrong: Adding resousre is called crashing