Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following statements about fast-tracking is TRUE?

A. Fast tracking is the process of increasing the schedule by overlapping various project tasks.

B. One of the advantages of fast-tracking is that it can often lead to reduced rework and reduces project risks.

C. None of the statements are true

D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.

E. Fast tracking involves performing activities sequentially

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/21
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable option is 

C. None of the statements are true

Alia Al Darmaki
by Alia Al Darmaki , Internship , Abu Dhabi Investment Authority

D Because A means where skipping tasks, and B is wrong

mohamed sabbah
by mohamed sabbah , Planning & Projects Control Manager , I.E.M.S.A. Construction

D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.

ahmmed Shahid Bolar RMP PMP  BE
by ahmmed Shahid Bolar RMP PMP BE , Senior planning and Scheduling Engineer , Dar Al Handasah

Right Answer is Option E.

Option A is wrong: Fast Track decreases schedule

Option B is Wrong: Doesnt reduce rework or reduce risk, May Increase Risk

Option D is wrong: Adding resousre is called crashing

 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.