Mohamed Abuhashem
par Mohamed Abuhashem , Chief Technical Office Engineer , Hassan Allam Construction

 7 days twice day and night

KIRANCHAND S
par KIRANCHAND S , Lead QA/QC Engineer , KAD Construction LLC

Min period is 7 days and if possible you can extend upto 28 days.It also depends on the curing technique we choose (Wet hessian cloth , Curing compund etc)

raheel bangash
par raheel bangash , civil inspector , obe architects

7 days...............................

marco farah ghattas
par marco farah ghattas , Civil Engineer , Qatar Power Construction

 in general cases7 days ......................

R MANESH RAVEENDRAN NAIR
par R MANESH RAVEENDRAN NAIR , site engineer( job performer) , NASAR SAID AL HAJRI

7 days for 50% strength .But for getting more strength need 28 days curing

riadh zemzem
par riadh zemzem , conception et calcul des structures en béton armé , B.I.E.S.CO

There is 28 day curing columns

vairamuthu subbiah
par vairamuthu subbiah , Sr.QC Inspector Civil , Galfar Engineering and Contracting

minimum requiremnt is 7 days . 

Zeiad Al-hachami
par Zeiad Al-hachami , Sr. Project Engineer , ExxonMobil Iraq Limited

Depanding on the kind of curing technique used. if normal watering is used, then 7 days minimum and left for 14-28 days prior to removing form depnending on the load on the column and its design 

Nirmalendu Sekhar Mishra
par Nirmalendu Sekhar Mishra , M.Tech Research Scholar , Indian School of Mines

7 days untill the form work is removed..28 days in total

Mohamed Noufal Pulikkal
par Mohamed Noufal Pulikkal , Quantity Surveyor/ Techincal Manager , HOWCON

Minimun 7 days in normal condition

Einston Johnson
par Einston Johnson , Project Engineer , National Piling Company

minimum Curing period is 7days