Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Pick up the correct sequence for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete :

A.    

1. Pouring of Concrete

2. Erection of form work

3. Curing of concrete

4. Removal of form work

 

B.    

1. Erection of form work

2. Pouring of concrete

3. Curing of concrete

4. Removal of form work

 

C.    

1. Removal of form work

2. Erection of form work

3. Pouring of concrete

4. Curing of concrete

 

D.   

1. Pouring of concrete

2. Curing of concrete

3. Erection of form work

4. Removal of form work

user-image
Question ajoutée par Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date de publication: 2016/05/10
Entisar Al Faisal
par Entisar Al Faisal , project construction engineer , City of Dearborn

In my knowledge. The correct answer is, B.

جعفر هندي زين السقاف
par جعفر هندي زين السقاف , مهندس أستشاري , مشاريع اﻻشغال العامة

Off course the correct sequence is option"B".

Nadjib RABAHI
par Nadjib RABAHI , Freelancer , My own account

The correct sequence is  : B

Mushreq Abdulmajeed
par Mushreq Abdulmajeed , Senior Project Supervisor , Lagoon Spring Company

...........OPTION   B ............

Nuridin Islam Diab
par Nuridin Islam Diab , Training Manager , Bbusinesss LLE

This is not my specialty................Thanks. 

michael ibao
par michael ibao , MACHINIST SUPERVISOR IN MOTORPOOL , somac contacting

Erection of form work ,Pouring concrete,curing of concrete,Removal of formwork

hatem labib
par hatem labib , Quality control manager , MISER consultant

-----------------------------------B-------------------------------------

Amr Gamal Anwar Hassan
par Amr Gamal Anwar Hassan , مهندس حاسب كميات , Shurfah Real Estate Development and Investment

sure the answer is option B

Marco Valente
par Marco Valente , Managing Director , ICME - Italian Contracting Middle East LLC

B is the only one correct sequence.

SAMIH ABBAS KOTTACKAL
par SAMIH ABBAS KOTTACKAL , STRUCTURAL ENGINEER TRAINEE , CASE STRUCTURAL ENGINEERS

THE ANSWER IS B.BUT I DIDN,T UNDERSTAND WHAT IS THE SIGNIFICANCE OF THIS QUESTION

Dennis Earl Robles
par Dennis Earl Robles , Site Architect , Fimat international Resources Inc.

Option B is the correct sequence

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?