Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

During updating, how to show planned and actual physical progress in columns?

I have to show the planned and actual phsical progress in addition to activity ID, name, start and end dates.

user-image
Question ajoutée par Muhammad Sajid Chaudhry , Sr. Manager Civil , Maple Leaf Cement Factory Ltd
Date de publication: 2013/07/17
Binil Paul
par Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

First you need to have a baseline plan which you create at the initial level Then make a copy of that and update the latter version using physical update percentage complete Now go to assign baseline and maintain baseline and in the updated program assign the initial plan (theoretically updated by update progress) as the primary baseline Now go to format columns and show the column BL physical percent compete and physical percent complete Now in the columns vie u can see both planned and actual Nw customise the name of columns as per your requirements Good day.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?