Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are the Project Manager for XYZ project. The scope of the project has been completed.

<p><strong>You receive a request for a new module to be developed as part of this project. What should you do next? </strong></p> <ol><li><strong>You should approach the Project sponsor and ask her for a new module to be developed as part of this project. </strong></li> <li><strong>You should approach the Senior Management and ask them for a new module to be developed as part of this project. </strong></li> <li><strong>You should send the request to Change Control Board for approval. </strong></li> <li><strong>Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.</strong></li> </ol>

user-image
Question ajoutée par Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
Date de publication: 2015/01/07
Elke Woofter
par Elke Woofter , Project Assistant , American Technical Associates

I would contact the Sr. Project Manager to get with the Project Sponsor

Wolf Klaas Kinsbergen
par Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

The scope is done so it has to be treated as a new (Part of the ) Project. I would ask senior management to take it up with the Project Sponsor or ask if I can take it up with her.

Irina Chepel
par Irina Chepel , Personal trainer , Freelancer

3, if not, otherwise4

Basit Ali
par Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

Option3

mohamed shaaban ramadan moursi moursi
par mohamed shaaban ramadan moursi moursi , project manager , PEAKS CONSTRACUTIONS & MAINTANANCE COMPANY

Option4

Mohamed Galal Hussein Ahmed Mohamed
par Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

4. As the scope is completed, the project is complete. Additional work should be done as part of a new project.

Since scope is completed so I assume the project has already been baselined, therefore the change should go to change control board for approval.

My answer is choice (3) You should send the request to Change Control Board for approval.

Muhammad Shakeel
par Muhammad Shakeel , CAD Design Manager , M/S zeeruk Intl.

The scope of work completed and Time duration for completion of project is also finish so any new assignment should treat as a new Project even this is an additional work of same project in this case i will ask senior management to take it up as a new Module.

 

If the scope of work completed before the planned time schedule and contractor not yet demobilize from site, so any new assignment from client should treat as an additional work of same project in this case i will ask senior management to take it up as a new Module and also send a request to change control Board for approval.

RAJ DAHIYA
par RAJ DAHIYA , Senior MEP Projects Manager , Trinity Engineering Services L.L.C.

Instead of denying to Customer, You should send the request to Change Control Board for approval hence, option "3" is more appropriate here.

ARUN BENADICK
par ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company

Option3. You should send the request to Change Control Board for approval.Because scope only completed. Still customer not accepted the Product. So Project is not completed.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?